High Density Customized Metso HP300 Parts

Original
price: Negotiable
minimum:
Total supply:
Delivery term: The date of payment from buyers deliver within days
seat: Beijing
Validity to: Long-term effective
Last update: 2017-12-30 02:39
Browse the number: 157
inquiry
Company Profile
 
 
Product details
Origin: Henan, China (Mainland)
Brand: Dashan
Model Number: HS-L-01
Type: bushings
Machine Type: Crusher
Certification: ISO9001
Material: Bronze
Processing Type: Casting
Use: Ore Mining
Characteristic: Durable and stable
Weight: Based on the model
Processing type:Centrifugal casting
Price: FOB
QC control: 100% inspected, accept third party inspection
Lubricant: Oiling
Drawing: Yes

Metso spare parts include:
upper head bushing ,lower head bushing, thrust bearing,eccentric bushing, socket liner, pision plate etc. All this bronze parts are imported wear parts of metso spare parts.
The role of this bronze bushing is slide bearings, have an irreplaceable role in the cone crusher.

Model :
Metso C series jaw crusher: C80 C100 C110 C125 C140 C160 C200
Metso (goldberg) GP series crusher : GP100,GP110,GP300,GP500
Metso (goldberg) HP series crusher : HP100, HP200, HP300, HP400, HP500, HP700, HP800 etc
The role of cone crusher spare parts are as slide bearings It has an irreplaceable role in the cone crusher. So, what is the specific role of the copper sleeve that makes something that requires attention?

Role cone crusher spare parts
Cone Crusher middle of a large gear assembly is cone crusher spare part, moving cone axis interpolation, the smaller gap of about 3 mm, under a larger gap of about 8 mm, can be measured with a thick fuse assembly, socket liner abrasion and wear of moving cone sphere will affect the gap, moving cone trajectory by decision.

How to replace the cone crusher spare parts :bronze bushing
1. Eccentric bushing
After locking filler hole drilling broken, then the eccentric bushing upside down, you can remove the bushing. Before installing the new one, you must check whether or not the eccentric sleeve hole size has cracked. When installing copper eccentric bushing, it is available in dry ice cooling. When pouring locking filler, eccentric and copper bushing must be at a temperature of about 70 degrees, eccentric and copper sleeve hole must be positive.

2. Upper head bushing and lower head bushing
Lower head bushing can be cut out, but make sure not to damage the moving cone bore. Upper head bushing can pull, and can be cooled with dry ice to speed up the pull-out speed. Dry ice can be used when installing copper cooling head bushing, at least 2 hours each, when fully cooled after, with its rings lift copper bushing, from under the rings to use flat gaskets to ensure dynamic cone copper sleeve edges and bottom edge parallel.

3. Countershaft bushing
Outer copper bushing sheath pulled by homemade devices removed within the copper sleeve can be removed using a center rod means hammering out the copper sleeve split out, you need to check the size of the hole in the creel is reasonable. When installing the countershaft bushing, use dry ice shrink at least 2 hours

Installing cone crusher spare parts
When installing the countershaft bushing, use dry ice shrink at least two hours. After installation is completed, you need to install the top screws, screw fastening needs painted with a professional plastic.
Total0bar [View All]  Related Comments
 
more»Other products

[ Products search ] [ favorites ] [ Tell friends ] [ Print ] [ Close ]